LNVAL-PRJ-MHT-0003Steel package — Hessler
Apr 26
May 26
Jun 26
Jul 26
Aug 26
Sep 26
Oct 26
Nov 26
⌕
SC-MHT-03: 5 plans proposed from its terms
March
↗
23 Mar 2026
§ Contract
Signed
Subcontract SC-MHT-03 · Hessler Stahlbau · €2,150,000.00
⬆ Sabine Krüger · via Web upload · 5 pages
April
↙
2 Apr 2026
✉
◐ Advance Payment Guarantee
€215,000.00
Advance payment guarantee KB-AG-5512 · Kinzigtal Bank · valid to 31 Jan 2027
✓ KB-AG-5512 expires · 304 days early
⬆ Email-in · via Email-in · 1 page
↙
2 Apr 2026
✉
⌶ Performance Bond
€215,000.00
Performance bond KB-PB-5513 · Kinzigtal Bank · valid to 30 Sep 2027
⬆ Email-in · via Email-in · 1 page
↙
20 Apr 2026
✉
⊜ Invoice
€215,000.00
HS-2026-0420 · advance 10% on SC-MHT-03 · due 20 May · Hessler
⬆ Email-in · via Email-in · 1 page
— 25 days —
May
↗
15 May 2026
◐ Payment Advice
€215,000.00
PA-MHT-0009 · settles HS-2026-0420
✓ advance 10% · against KB-AG-5512 · 5 days early
⬆ Michael Torres · via Web upload · 1 page
— 116 days —
September
↙
8 Sep 2026
▶ Delivery Note
184 t
LS-HS-2291 · tranche 1 · columns & primary beams L1–L13
✓ tranche 1 · columns & primary beams · 2 days early
⬆ Lena Hoffmann · via Mobile camera · 1 page
25 Sep 2026
⌮ Inspection Report
Pass
Weld inspection level 12 · 38 joints · ultrasonic
✓ weld inspection level 12 · on the day
⬆ Markus Schäfer · via Web upload · 1 page
October
↙
8 Oct 2026
✉
⊜ Invoicev2 ⟲
€268,000.00
HS-2026-1006 · interim 1 on SC-MHT-03 · due 5 Nov · Hessler
⬆ Email-in · via Email-in · 1 page · v2 of 2
↙
12 Oct 2026
✉
⊝ Method Statement
MS-HS-014
Steel erection levels 14–22 · tower crane TC2 · Hessler
⬆ Email-in · via Email-in · 2 pages
5 Nov 2026 · planned
⚑ Today · 12 Nov 2026
17 Nov 2026 · planned
18 Nov 2026 · planned