LNVAL-PRJ-MHT-0007Site reports & inspections
Nov 26
⌕
October
16 Oct 2026
⏄ Daily Site Report
Level 13 steel complete
Weekly site report wk 42 · 14 photos · 86 on site · rain 1 day
⬆ Lena Hoffmann · via Web upload · 2 pages
21 Oct 2026
⌮ Inspection Report
Pass
Core walls L16–L18 handed over to steel · Hessler, Kranich present
⬆ Markus Schäfer · via Web upload · 1 page
23 Oct 2026
⏄ Daily Site Report
Façade anchors L12–L15 set
Weekly site report wk 43 · 12 photos · 91 on site
⬆ Lena Hoffmann · via Web upload · 2 pages
28 Oct 2026
⌭ Programme Updatev3 ⟲
Programme rev 3
Completion 04 Aug 2028 · 14 days later than rev 2
⬆ Jonas Weber · via Web upload · 1 page · v3 of 3
30 Oct 2026
⏄ Daily Site Report
Stone batch 1 quarantined
Weekly site report wk 44 · 9 photos · 88 on site · NCR-MHT-004
⬆ Lena Hoffmann · via Web upload · 2 pages
November
5 Nov 2026
⊛ Meeting Minutes
Site coordination meeting #31
9 attendees · 7 actions · façade anchor inspection set for 19 Nov
⬆ Lena Hoffmann · via Web upload · 1 page
6 Nov 2026
⏄ Daily Site Report
Core walls cast to level 20
Weekly site report wk 45 · 15 photos · 94 on site
⬆ Lena Hoffmann · via Web upload · 2 pages
9 Nov 2026
◉
◉ Video
4:12
Site walk L12–L16 · façade anchors and stone podium
⬆ Lena Hoffmann · via Mobile camera
11 Nov 2026
◌ Voice Message
▂▃▅▇▆▄▂▁▂▄▆▇▅▃▂▁▂▃▅▆▄▂▁▃▅0:44
“Katharina, hier ist Lena von der Baustelle…”
⬆ Lena Hoffmann · via Mobile camera
⚑ Today · 12 Nov 2026
19 Nov 2026 · planned
Oct
Nov